EXPLORATION & DEVELOPMENT

REZ recalculates Mount Mackenzie outlook

Stronger 2020 gold price delivers doubling of earnings from low-cost Queensland development

This article is 5 years old. Images might not display.

After taking into account the estimated $13 million capital cost, operating cashflow is now estimated at $67.6 million, a significant boost based on December's scoping study.
 
The junior, which has had the Central Queensland project for the past five years, is now working on pit optimisation, mine scheduling and a revised resource estimate to underpin a proposed 300,000-500,000 tonne per annum development, with the work scheduled to be completed within one month.
 
A 600,000tpa option will also be examined as part of a detailed feasibility study. Reserve drilling is also being planned.
 
Based on $2000/oz gold price, the 2019 study helped defined a low-cost, shallow open-cut development with an on-site gold plant, initially a heap leach operation, before transitioning to a bulk sulphide concentrate project, with further metallurgical investigations planned into the floatation process used at Evolution Mining's nearby Mt Carlton operation.
 
The 2020 revised study used a pit based around a $2400/oz gold price.
 
The revised scoping study looked at recovery of 43,500oz gold and 270,000oz silver over around four years of mine life at estimated C1 cash costs of $1400/oz. 
 
Mount Mackenzie resources are estimated at 100,000oz gold and 624,000oz silver, with the North Knoll and South West Slopes zones calculated using a $1700/oz price.
 
There is potential for gold-copper mineralisation beneath the shallow Mount Mackenzie resources. 
 
The project, which is covered a granted mining lease, contains several prospects that require additional drilling, including the Instinct porphyry polymetallic target 1km away.
 
Outside the development lease are the Sphinx and Quinine Gully gold and base metal targets at the Clive Creek prospect.
 
REZ's other focus in the Menzies goldfield in Western Australia, where it recently defined a 2.5km-long, 450m wide 100 parts per billion gold anomality in its first regional drilling program at East Menzies.
 
REZ shares were last traded up 14% at 1.6c, valuing the company at $6.2 million.

 

Expert-led Insights reports and Analytics tools built on robust data, rigorous analysis and expert commentary covering mining Risk, Projects, ESG, Leadership, and Investor Sentiment.

Expert-led Insights reports and Analytics tools built on robust data, rigorous analysis and expert commentary covering mining Risk, Projects, ESG, Leadership, and Investor Sentiment.

editions

ESG Index 2025: Benchmarking the Future of Sustainable Mining

The ESG Index provides an in-depth evaluation of the ESG performance of 60+ of the world’s largest mining companies. It assesses companies across 10 weighted indicators within 6 essential ESG pillars.

editions

Leadership Insights 2025

Leadership Insights reveals key trends in priority mining issues through interviews with 15+ top mining company executives and an industrywide survey.

editions

Mining IQ Risk Analytics

Risk Analytics offers interactive access to World Risk Insight data, allowing you to customise risk views, benchmark jurisdictions, explore data behind scores and read expert commentary to guide your decision-making.

editions

Project Pipeline Index 2025

View our 50 top mining projects, handpicked using a unique, objective selection process from an expanded database of 600+ global assets.