Queensland lays out Adani timeline

Queensland Premier Annastacia Palaszczuk announces timeline for decisions on Adani approvals

This article is 6 years old. Images might not display.

This is not to say the government has to approve those plans. It just means it has to make a decision on them.

Under this timeline the Black-Throated Finch Management Plan decision is to be handed down by May 31 and the deadline for the Groundwater Dependent Ecosystem Management Plan is June 13.

The Queensland coordinator general is also expected to release the government's target dates for finalising the royalties agreement, the deed of access and sublease for the rail, and other relevant infrastructure agreements.

Little more than one week ago the Queensland Department of Environment and Science said it wanted to conduct another review of the GDEMP.

This came after the federal government had granted its approval of the groundwater plan using CSIRO and Geoscience Australia advice.

When Adani received its federal groundwater approval on April 9 it was 3091 days into its approval process. It took 2891 days to build the Sydney Harbour Bridge.

Palaszczuk called the announcement of the timeline a "breakthrough" in the project.

More cynical coal industry watchers might suggest the real breakthrough came on May 18 when Labor had its head handed to it federally over its equivocal views on the Adani mine.

Adani Mining CEO Lucas Dow said he welcomed Palaszczuk's timeline announcement.

"We will work closely with the Queensland government to achieve these timeframes and we expect that the Department of Environment and Science will now finalise these plans within weeks, not months," he said.

"This is a positive step towards construction of the mine and rail project.

"We will continue to uphold our end of the bargain and will undertake the necessary work to meet these timeframes and we're looking forward to the Queensland government doing the same.

"This will bring the lengthy, independent and rigorous two-year review process for these management plans to an end.

"DES has been reviewing the groundwater management plans for more than two years, across 11 versions.

"In addition pre-eminent scientific bodies CSIRO and Geoscience Australia have also conducted reviews of the groundwater management plans.

"Over the past two years, seven versions of the Black-Throated Finch Management Plan have also been submitted to DES, consisting of more than 1000 pages of advice. These have been assessed and verified by more than 10 different scientists, five environmental consultancy groups and even a Land Court judge."

Expert-led Insights reports and Analytics tools built on robust data, rigorous analysis and expert commentary covering mining Risk, Projects, ESG, Leadership, and Investor Sentiment.

Expert-led Insights reports and Analytics tools built on robust data, rigorous analysis and expert commentary covering mining Risk, Projects, ESG, Leadership, and Investor Sentiment.

editions

ESG Index 2025: Benchmarking the Future of Sustainable Mining

The ESG Index provides an in-depth evaluation of the ESG performance of 60+ of the world’s largest mining companies. It assesses companies across 10 weighted indicators within 6 essential ESG pillars.

editions

Leadership Insights 2025

Leadership Insights reveals key trends in priority mining issues through interviews with 15+ top mining company executives and an industrywide survey.

editions

Mining IQ Risk Analytics

Risk Analytics offers interactive access to World Risk Insight data, allowing you to customise risk views, benchmark jurisdictions, explore data behind scores and read expert commentary to guide your decision-making.

editions

Project Pipeline Index 2025

View our 50 top mining projects, handpicked using a unique, objective selection process from an expanded database of 600+ global assets.