BEADELL Resources has made a decision to spend US$28 million upgrading its Tucano gold processing plant in Brazil so as to recover an additional 190,000 ounces that would otherwise not be produced.

Beadell beefing-up Tucano Beadell beefing-up Tucano Beadell beefing-up Tucano Beadell beefing-up Tucano Beadell beefing-up Tucano

The addition of plant including a ball mill, leach tank, thickener and sparging system will allow the company to process a mix of sulphide and oxide ore and increase recoveries from 88% to 93%.