First iron exports from Pardoo delayed

THE first iron ore exports from Atlas Iron’s flagship Pardoo project in the Pilbara will be delayed for up to three months over an environmental appeal.

First iron exports from Pardoo delayed First iron exports from Pardoo delayed First iron exports from Pardoo delayed First iron exports from Pardoo delayed First iron exports from Pardoo delayed

The target date for first iron ore shipment from the project has been pushed back from October 2008 to December 2008 while the company awaits the ruling of an appeal lodged by Atlas over conditions