Highfield sees a return to growth with key Muga potash approval in hand

HAVING been put in the back paddock for the past 3-4 years for the sins of a long drawn out environmental permitting process in Spain, Highfield Resources will be hoping for some market love to return its way as the final operating permits for its Muga potash project appear to now be within reach.

Highfield sees a return to growth with key Muga potash approval in hand Highfield sees a return to growth with key Muga potash approval in hand Highfield sees a return to growth with key Muga potash approval in hand Highfield sees a return to growth with key Muga potash approval in hand Highfield sees a return to growth with key Muga potash approval in hand

The fertiliser thematic has been growing in recent times

Highfield got the key environmental permit for Muga in June and has been guiding it should get the mining and construction permits within 12-18 months of getting the green tick.