Talison opens CGP2 expansion

AFTER four years and A$320 million, Talison Lithium officially celebrated the start-up of its new Chemical Grade Plant 2 expansion yesterday, plant, the latest milestone for Western Australia’s longest continuously operated mine, with plans for future expansions very much alive.

Talison opens CGP2 expansion Talison opens CGP2 expansion Talison opens CGP2 expansion Talison opens CGP2 expansion Talison opens CGP2 expansion

The new CGP2 is in commissioning.

The mine is now ramping up to an annual output of 1.3 million tonnes, and it has plans to more than double production next decade to some 2.8Mt… if the market demand is there.