Rio goes underground in Utah

RIO Tinto has approved US$55 million in development capital to start underground mining and expand production at its Kennecott copper operations in Utah.

Staff reporter
Rio Tinto's Kennecott operation in Utah

Rio Tinto's Kennecott operation in Utah

Kennecott, just outside Salt Lake City, has been operating since 1903 and the Bingham Canyon pit is the world's largest man-made, open pit excavations in the world, visible from space.

Initial underground mining will focus on an area known as the Lower Commercial Skarn (LCS), which will deliver a total of around 30,000t of copper from early 2023 through to 2027.

LCS has a resource of 7.5 million tonnes at 1.9% copper, 0.84 grams per tonne gold, 11.26gpt silver and 0.015% molybdenum and a reserve of 1.7Mt at 1.9% copper, 0.71gpt gold, 10.07gpt silver and 0.044% molybdenum.

Full underground production is expected in the second half of next year.

"This investment will allow us to quickly bring additional volumes of high-quality copper to the market and build our knowledge and capabilities as we evaluate larger scale underground mining at Kennecott," Rio Copper chief executive Bold Baatar said.

"We are progressing a range of options for a significant resource that is yet to be developed at Kennecott, which could extend our supply of copper and other critical materials needed for electric vehicles and renewable power technologies."

The company is also trialling underground battery electric vehicles, supplied by Sandvik Mining and Rock Solutions.

"Trialling underground battery electric vehicles is an exciting step in our work to create a safer workplace for our employees, increase the productivity of the mine and reduce emissions from our operations. We look forward to seeing their potential for deployment," Baatar said.

Existing underground infrastructure is currently being extended to enable early access to the next underground resource and undertake characterisation studies.

A feasibility study to inform decisions on the next phase of underground production is expected to be completed in 2023. This will be one of several potential stages currently being investigated.

Feasibility studies are also being progressed to extend open pit mining at Kennecott beyond 2032.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining News Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining News Intelligence team.

editions

MiningNews.net Research Report 2024

Access a multi-pronged tool to identify critical risks and opportunities in Australia’s mining industry.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on the quarterly mining IPOs and secondary raisings data and mining equities performance tables with an annual Stock Exchange Comparisons supplement.

editions

Mining Journal Intelligence World Risk Report 2023 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 121 jurisdictions globally, built on 11 ‘hard risk’ metrics and an industrywide survey.