Ora Banda nearly halves Davyhurst cost

ORA Banda Mining has almost cut in half the expected cost of refurbishing the Davyhurst processing plant north of Kalgoorlie, with the engineering, procurement, and construction management estimate put at A$8.5 million within a timeframe of 24 weeks.

Ora Banda nearly halves Davyhurst cost Ora Banda nearly halves Davyhurst cost Ora Banda nearly halves Davyhurst cost Ora Banda nearly halves Davyhurst cost Ora Banda nearly halves Davyhurst cost

Ora Banda heading down the track to targeted production in 2021 north of Kalgoorlie

The previous high level estimate provided to administrators after Ora Band's forerunner Eastern Goldfields failed was $15 million for the 1.