Another delay at Douglas

DELAYS continue to plague Iluka’s $A270 million Douglas mineral sands project in the Murray Basin in Victoria with confirmation that the mineral separation plant (MSP) being constructed by Roche Mining will take at least eight months longer than originally anticipated.

Another delay at Douglas Another delay at Douglas Another delay at Douglas Another delay at Douglas Another delay at Douglas

The original engineering, procurement and construction contract signed by Roche specified a completion date of October 2005 for the MSP however Roche advised Iluka that it now expects to complete the