GR Engineering and Eastern Goldfields were in court yesterday with both sides claiming partial wins.

GR, Eastern Goldfields sent to arbitration GR, Eastern Goldfields sent to arbitration GR, Eastern Goldfields sent to arbitration GR, Eastern Goldfields sent to arbitration GR, Eastern Goldfields sent to arbitration

In July 2017, GR started proceedings in the Supreme Court of Western Australia to claim A$9.9 million, plus interest and costs, over the Davyhurst plant refurbishment contract.

The price for the contract, entered into in September 2016, was $18.5 million, including variations for additional works.

Eastern Goldfields said at the time that the contract price was $12.5 million, and it had paid $10.4 million.

GR issued Eastern Goldfields with a statutory demand for $6.6 million, and Eastern Goldfields alleged the wrongful suspension of works and raised an associated offsetting claim for delay costs of about $6.8 million in seeking to set aside the statutory demand.

Eastern Go...